Name: Technical Assistance and Inspection of Works for the Comahue-Cuyo Interconnection, Northern Section
Brief Description: The works included: a) a 188 km long 500 kV extra-high voltage line and a 7 km long 200 kV high voltage line between the new line; and b) the transformer stations in Greater Mendoza (expansion) and the new transformer station in Los Reyunos, both at 500 kV, and the expansion of the latter to 220 kV. The work included the review of the contractor’s socio-environmental management plan and monitoring of its implementation.
Location: Mendoza Province, Argentina
Year: 2009-2011
Client: Coordinating Unit for Project Execution (UCEP – CAF) for the Comahue-Cuyo Interconnection