Name: Basic studies, execution of basic engineering, preparation of bidding documentation, and environmental impact study for the 500 kV Rodeo transformer station-La Rioja Sur transformer station interconnection works (Section V)
Brief description: The tasks performed were for the construction of:
The extra high voltage (500 kV) single-strand transmission line between the Rodeo transformer station (San Juan) and the La Rioja Sur transformer station (La Rioja), approximately 350 km long.
The expansion of the La Rioja Sur transformer station to allow the triple-strand output to the Rodeo transformer station.
The 500 kV yard at the Rodeo transformer station, in accordance with the existing preliminary design.
Included the preparation of the general and technical specifications, and the environmental impact study for the entire transmission line and the corresponding transformer stations.
Location: San Juan and La Rioja Provinces, Argentina.
Year: 2017-2019
Client: Comité de Administración del Fondo Fiduciario para el Transporte Eléctrico Federal (CAF)