Type of work: Executive project, Direction, Inspection and Detailed Engineering of the works. 

Executive project, Direction, Inspection and Detailed Engineering of the works: earth dam 115 m high and 12,000,000 m3 in volume. Take, Spillway for 3,000 m³ / sec. 1,000,000 kW Hydroelectric Power Plant. Download channel. Temporary villa. River diversion works through 2 tunnels of 2,000 m in length and 9.00 m in diameter. a) Review and adjustment of the Executive Project; b) Technical assistance in all phases of bidding and contracting of works; c) Preparation of detailed plans for civil works; d) Preparation of detailed plans for the installation of machinery and electromechanical equipment; e) Technical and administrative management of the works; f) Inspection and control of manufacturing, testing, shipping and transportation of electromechanical machinery and equipment; g) Technical assistance during the commissioning of the plant and the warranty period.