Type of work: Technical assistance, project monitoring and supervision of the detailed engineering of the works. 

a) El Huemul Project: Treatment of crude oil to meet the specifications required in Pico Truncado (Y.P.F.): 3,000 m³ / day of crude oil treated for a specification of 0.5% BSW. Treatment of oily water to be suitable for reinjection: 5,000 m³ / day of treated water. Measurement of the volume of crude in Pico Truncado. Auxiliary services. Fuel gas. Extension of the fire network. Construction of a new 10 MVA transformer substation. b) Cañadón Alfa Project: New gas treatment plant, with a capacity of 4,000,000 m³ / day and forecast to reach a maximum capacity of 6,700,000 m³ / day. New compression facilities for medium pressure (MP) with a capacity of 7,000,000 m³ / day, which will raise the pressure from 36 kg / cm² to 73.5 kg / cm². Expansion of services, to reach the new total capacity of the plant. Underground power line from the Cullén river. Fire fighting services: tanks, pumps and network. Waste gas burning system. Drainage system. New gas pipelines (3,000 m of 10 “).