Name: Technical assistance and inspection of the works corresponding to the opening of the 345 kV Cobos-Andes extra-high voltage line, the Altiplano sectioning station, and complementary works for the interconnection of the Cauchari I, II, and III Solar Farms (Total capacity: 300 MW).
Brief description: The works included the corresponding assembly of power equipment for the 345 kV gas-insulated substation, the alternating current and direct current auxiliary service transformers, their primary and secondary connections, control panels, auxiliary panels and associated cabinets, battery chargers, stationary batteries, etc.
Location: Province of Salta, Argentina.
Year: 2018-2021
Client: Interandes S.A.”